Building Project – Day #15

  Stage 2, commence! This week the main office is almost finished (save carpets, and a few cupboard doors). Yesterday, Paul and Brian began work dismantling/demolishing the pastors’ office ready for stage 2 to begin that side in the coming days. View the plan for our new office layout here. See...

Continue reading

Building Project – Day #8

New walls and new paint! If you walk into the main office, you may think it’s gotten a little smaller… in fact, it has! A new wall has been constructed on the western side of the office, bringing the total space inside down from ± 27m² to ± 21m². This...